Interfaith Build
This is the fifth house sponsored by the Interfaith Advisory Council (IAC) since the council’s creation and the seventh house sponsored by the interfaith community in total.
About the Interfaith Advisory Council:
IAC works to fulfill one of the highest aims of Habitat for Humanity International, which is to challenge world religious leaders to work together to end poverty on the planet, using decent shelter as a transformational and foundational strategy to accomplish that vision. IAC is committed to action by building and advocating for decent, affordable housing in our community.
Meet the Future Homeowner, Shalin B.
“I’ve learned a ton, and I’ve met a lot of caring, genuine people along the way. From classes to construction sites, the people who volunteer and teach are very informative and help prepare you for home ownership before you move into your house.”
Shalin B., Habitat Future Homeowner
Phase 1
Homesite Selection
Homeowner selects homesite from available Habitat lots. Homeowners are paired with their sponsor.
Phase 2
Groundbreaking
During the groundbreaking, the foundation is completed and the block work is laid.
Phase 3
Crawl Space and Floor System
Volunteers install moisture barrier and insulation in crawl space.
For the floor system, the floor joists are installed, more foam insulation is filled in between joists and band boards, and OSB board is laid for the flooring. Black paper is laid on the two porches to help maintain the longevity of the home.
Phase 4
Walls
Wall Prep: Volunteers build wall components (king jack studs, California corners, headers, etc.) and layout 2 x 4 location on the top and bottom plates of each wall.
Wall Building: Wall components are nailed together on top and bottom plates with 2 x 4s. This is completed for both interior and exterior walls.
Wall Raising: Volunteers raise, level, and secure the walls. Exterior walls go up first, followed by the interior.
Trusses: OSB boards are laid on first and last trusses to attach the siding.
Phase 5
Doors and Windows
Volunteers install windows and doors.
Phase 6
Internal Mechanics
Plumbing, electric, insulation, and dry wall are installed.
Phase 7
Pre-insulation
Pre-insulation is installed on exterior walls, doors, windows, ceiling, and floors. Baffles are put in to circulate airflow.
Phase 8
Painting
Volunteers paint the walls and ceiling. Corners and edges are cut out first, then roll the ceilings, and then the walls.
Phase 9
Cabinets and Appliances
Cabinets and countertops installed.
Later, refrigerator, stove, microwave, dishwasher, garbage disposal, and washer & dryer are installed.
Phase 10
Trim Work and Flooring
Trim around windows and doors are completed. Interior doors are also installed. Vinyl and carpet are laid.
Phase 11
Exterior Concrete
Exterior concrete parking pad and sidewalks are poured.
Phase 12
Yard Prep
The yard is prepared for grass seed sewing.
Phase 13
Dedication
Homeowner and community members come together to bless and dedicate the home, complete with a ribbon cutting.